Project Itself

9/28 - 10/2 -- Gather articles and do research on setting up proposed servers/network COMPLETED

10/5 - 10/9 -- Set up mail server, FTP server, and workstations IN PROGRESS

10/12 - 10/16 -- set up firewall/DHCP/router server

10/19 - 10/23 -- get virtual network up and running, troubleshoot any issues

10/26 - 10/30 -- research hacking techniques and using Kali Linux for penetration testing

November -- penetration testing; router tweaking; documenting finds

12/1 - 12/8 -- Prepare PowerPoint Presentation on findings