9/28 - 10/2 -- Gather articles and do research on setting up proposed servers/network COMPLETED

10/5 - 10/9 -- Set up mail server, FTP server, and workstations COMPLETED

10/12 - 10/16 -- set up firewall/router server COMPLETED

10/19 - 10/23 -- get virtual network up and running, troubleshoot any issues FAILED

10/26 -- get virtual machines to communicate with each other, set up DNS server COMPLETED

10/27 - 10/30 -- research hacking techniques and using Kali Linux for penetration testing COMPLETED

November -- penetration testing; router tweaking; documenting finds MOSTLY COMPLETED

12/1 - 12/8 -- Prepare PowerPoint Presentation on findings IN PROGRESS